November 29, 2015
The Liberty Lake Splash
23403 E Mission Ave Ste 102
PO Box 363
Liberty Lake, WA 99019
Phone: 509-242-7752
Fax: 509-927-2190
News Blog Business Community Opinion Sports

More News

Property tax increase deferred for 2016

View the December 2015 Splash

Eat, Shop & Be Merry: Shop local for these great gifts

Eat, Shop & Be Merry: Your pick of the menu
Try these standout orders at local restaurants

Eat, Shop & Be Merry: 12 Gifts of Christmas
Turn materialism into generosity this season

Eat, Shop & Be Merry: Wrap up your shopping creatively

Eat, Shop & Be Merry: Celebrating the season
Local personalities create meaningful moments through holiday traditions

A Cup of Joe: Comprehensive consultation
Dohrn advises city in development deliberations

November Council Recap: August vote targeted for community center/pool

LLPD and SVFD Reports

News Brief

Dunne defeats Beckett to earn re-election to council

Search the News Archive Search the News Archive

Summer construction report
8/1/2013 2:22:31 PM

The long list of summer projects inside the city of Liberty Lake appears ready to launch into motion in August. The following status report was provided July 29 by City Engineer Andrew Staples.

Harvard Roundabout - Construction of single lane roundabout at Harvard Road, Mission Avenue intersection. 

Anticipated dates of work: The demolition and construction phase of this project is tentatively scheduled to get under way Aug. 17, with work wrapping up over the course of about eight weeks.

Traffic impact: Reduced lanes on the north side of the Harvard Bridge, flaggers and signage will direct traffic. 

Mission and Valleyway street maintenance - Overlay work on Mission Avenue from Molter Road to King James Lane and on Valleyway Avenue from Molter to Bella Lago Lane.

Anticipated dates of work: The bid on this project has been awarded, and work is likely to begin in mid-August. Once work begins, it should take about two weeks.

Traffic impact: Minor delays will be caused by reduced lanes or detours. Flaggers will be directing traffic at the work site.

Sprague Trail - Construction of two 10-foot wide path segments on Sprague Avenue and Neyland Drive. 

Anticipated dates of work: The bid on the project has been awarded, and work is scheduled to begin on Aug. 5.

Traffic impact: Minimal impact with traffic control directing drivers around the construction along the north shoulder of the road.

Liberty Lake Fields - Improvements to the field east of Liberty Lake Elementary including construction of a pair of baseball fields, a 79-space parking lot, a small picnic shelter and concrete walking paths.

Anticipated dates of work: The project will be awarded in late summer, meaning a late summer and fall construction timeframe.

Traffic impact: None.

Note: The city of Liberty Lake will post traffic revisions on its website, as applicable. 