October 30, 2014
The Liberty Lake Splash
23403 E Mission Ave Ste 102
PO Box 363
Liberty Lake, WA 99019
Phone: 509-242-7752
Fax: 509-927-2190
Map
News Blog Business Community Opinion Sports

More News

A Cup of Joe: Awareness patrol
LLPD's Thomas on front lines in battle against drugs, alcohol

LL set for tidy transition in waste services

Lake gets new water filters
Water district, county work to keep Liberty Lake clean

Mayor introduces 2015 budget

Police Report

Mayor introduces 2015 budget, council hears parks survey results

Council hears overview of utility tax, property tax impacts

View the October 2014 Splash

Cover Story: A circle of admirers
Harvard Road roundabout earns stellar reviews in first year

Workshop explores possible changes to city sign code

LLSWD steps up as lead agency in Lakemore proposal

A Cup of Joe: Plant manager
Cary oversees flourishing foliage as city horticulturist

Police Report

City switching to private option for waste

News Briefs

Olander steps down, Council prepares to explore sign code

Search the News Archive Search the News Archive

Summer construction report
8/1/2013 2:22:31 PM

The long list of summer projects inside the city of Liberty Lake appears ready to launch into motion in August. The following status report was provided July 29 by City Engineer Andrew Staples.

Harvard Roundabout - Construction of single lane roundabout at Harvard Road, Mission Avenue intersection. 

Anticipated dates of work: The demolition and construction phase of this project is tentatively scheduled to get under way Aug. 17, with work wrapping up over the course of about eight weeks.

Traffic impact: Reduced lanes on the north side of the Harvard Bridge, flaggers and signage will direct traffic. 

Mission and Valleyway street maintenance - Overlay work on Mission Avenue from Molter Road to King James Lane and on Valleyway Avenue from Molter to Bella Lago Lane.

Anticipated dates of work: The bid on this project has been awarded, and work is likely to begin in mid-August. Once work begins, it should take about two weeks.

Traffic impact: Minor delays will be caused by reduced lanes or detours. Flaggers will be directing traffic at the work site.

Sprague Trail - Construction of two 10-foot wide path segments on Sprague Avenue and Neyland Drive. 

Anticipated dates of work: The bid on the project has been awarded, and work is scheduled to begin on Aug. 5.

Traffic impact: Minimal impact with traffic control directing drivers around the construction along the north shoulder of the road.

Liberty Lake Fields - Improvements to the field east of Liberty Lake Elementary including construction of a pair of baseball fields, a 79-space parking lot, a small picnic shelter and concrete walking paths.

Anticipated dates of work: The project will be awarded in late summer, meaning a late summer and fall construction timeframe.

Traffic impact: None.

Note: The city of Liberty Lake will post traffic revisions on its website, www.libertylakewa.gov as applicable. 